Driving Range update - Dec 22
Construction of the shed was completed on Wednesday 14th December (it took CPR Sheds 8 days) and since then JetLine has poured a new cart path from the shed to the the existing brick paving at the top of the range.
Electricals, Lighting, security alarms, security cameras, and padding will be installed middle of January after the festive break.
Range mats and bay dividers were received earlier in the month and will be installed at the same time.
Max and his team will be renovating the driving range grass areas in the coming months.